AI Compute Deal Ledger · BTDR · Free Dataset · CC BY 4.0

Bitdeer Technologies: The AI Deal Record

Every Bitdeer Technologies deal in the ledger, with the source on every row. Binding contract value: $4.7B across 121 MW of contracted IT capacity. Guarantees and equity are totalled apart from contract value, and snapshot disclosures (backlog restatements, order intake, program envelopes) are listed but never summed.

Contract value

$4.7B

1 binding contract, base terms

Binding capacity

121 MW

contracted IT load with disclosed MW

Not binding

·

0 LOI / framework / reported

Deal by Deal

2026-08-04Binding

Bitdeer Technologies (Provider) · Volta Infra (Buyer)

Value
approximately $4.7B
$8B with all options
Capacity / term
121 MW · 16y
$2.43M per MW-year
First revenue
2026-12

Surfaced this run via general web sweep, not the EDGAR watchlist (Bitdeer is not on the ledger's watchlist). Predates this run by three weeks; missing from the ledger until now, same pattern as the TeraWulf-Anthropic and Duos-Axe Compute gaps found in prior runs. Reconfirmed unchanged in Bitdeer's 2026-08-26 'July 2026 Production and Operations Update' 6-K exhibit. That same update also disclosed an AI Cloud facility (A102) in Malaysia 'fully committed with over $800 million in expected revenue' with no named counterparty or MW figure given; logged to candidates.json rather than given a row.

Conditions: 16-year colocation lease at Bitdeer's Tydal, Norway campus (a former cryptomine), signed with Volta subsidiary Volta Tydal AS; approximately $202/kW/month over the base term, with electricity pass-through to the tenant. An 8-year renewal option extends the potential total to approximately $8.0B over 24 years. Affiliates of J.P. Morgan and another unnamed global financial institution are expected to issue about $1.3B in letters of credit as credit support; the lease is subject to customary closing conditions. Phase 1 (of 133MW gross / 121MW IT capacity) targeted online by 2026-12-31, phase 2 by 2027-03-31. Bitdeer's own disclosure names only 'a subsidiary of Volta Infra' as tenant; it does not name Volta's own end customer. Bloomberg reported, citing sources, that Volta's compute customer here is Anthropic under a separate $10B/6-year compute-services agreement between Volta and Anthropic; that leg is now its own row, volta-anthropic-tydal-compute-2026-08, entered 2026-10-12 once Volta's own press release surfaced as a primary source for the deal terms. Arithmetic check: $202/kW/month x 121,000kW x 12mo x 16yr = ~$4.69B, reconciling almost exactly to the stated $4.7B base figure.

Part of the free AI Compute Deal Ledger by Regards of Wallstreet, licensed CC BY 4.0. Cite it, chart it, link it.