SB Energy: The AI Deal Record

Every SB Energy deal in the ledger, with the source on every row. Binding base-term value: $105B across 4.25 GW of contracted IT capacity. Snapshot disclosures (backlog restatements, order intake, program envelopes) are listed but never summed.

Binding value

$105B

1 binding deals, base terms

Binding capacity

4.25 GW

contracted IT load with disclosed MW

Not binding

·

0 LOI / framework / reported

Deal by Deal

2026-09-02BindingSnapshot, not summed↻ Circular

SB Energy (Provider) · OpenAI (Buyer) · SoftBank (Buyer)

Value
$439B
Capacity / term
8.8 GW
First revenue
not disclosed

SNAPSHOT ROW, excluded from summed aggregates (basis: total_backlog). Surfaced from the EDGAR watchlist hit on SB Energy's S-1 (filed 2026-09-01/02). This is SB Energy's own rollup of its signed data-center leases and is not additive with nvidia-openai-sb-energy-ohio-2026-08 (Nvidia's $105B residual-value guarantee on the initial 4.25 GW-IT phase of the same OpenAI Ohio lease) or with any other row: they describe different instruments (guarantee ceiling vs. lease backlog) against overlapping capacity, so summing them would double count the Ohio campus. Scale check: $439B backlog against a company with ~$4B of debt and a $3.8B accumulated deficit and no operating data center yet is consistent with the pattern already established by Stargate ($500B program envelope) and Applied Digital ($36B backlog on 1.41GW); AI-infrastructure backlogs routinely run far ahead of revenue at this stage of the cycle, and SB Energy's own S-1 states the same (~$1B converts in 24 months, ~$357B beyond year 8). Arithmetic check: $430B data-center backlog / 8.8GW-IT over the disclosed lease terms (mostly 20-year OpenAI leases) is broadly consistent with the $13.3M/MW/yr full-stack rate already reconciled for OpenAI-Oracle Stargate capacity, though SB Energy's mix includes lower-cost triple-net shell leases (the Cosmos campus alone reconciles to $2.5B / 50MW / 15yr = ~$3.3M/MW/yr, inside the ledger's sanity band). Cross-source: SEC S-1 (primary) plus independent Yahoo Finance and Latitude Media reporting citing the same $439B/8.8GW-IT/8.0GW-IT figures. Counterparty note: 'buyer' role split across OpenAI (Ohio, ~8.0GW-IT) and SoftBank (remaining balance including Cosmos); the S-1 itself does not further break out the balance by named tenant beyond SoftBank affiliates, so this row does not assert a precise split beyond the two figures given in conditions.

Conditions: SB Energy's S-1 registration statement (filed for a planned Nasdaq/Nasdaq Texas listing as SBE) discloses $439B of total backlog under binding contracts, of which approximately $430B is from data centers, against 8.8 GW-IT of signed leases concentrated in two customers: OpenAI (approximately 8.0 GW-IT across 17 buildings, 20-year leases, at the Ohio PORTS-Pike campus) and SoftBank (the balance, including the Cosmos Technology Campus in Travis County, TX: 50 MW-IT under a 15-year triple-net lease with expected aggregate rent of $2.5B, financed by $999M of 8.875% senior secured notes due 2031 issued by project subsidiary SE Cosmos LLC, first rent targeted Q4 2026). The backlog is heavily back-loaded: roughly $1B is expected to convert to revenue in the next 24 months, with about $357B beyond year 8. SB Energy reported approximately $4B of debt and a $3.8B accumulated deficit as of the filing.

2026-08-17Binding↻ Circular

Nvidia (Financier) · OpenAI (Buyer) · SB Energy (Developer)

Value
up to $105B
Capacity / term
4.25 GW · 20y
$1.24M per MW-year
First revenue
2028

Surfaced via the EDGAR watchlist hit on Nvidia's 8-K filed 2026-08-17. This formalizes and supersedes the reported-only nvidia-openai-backstop-talks-2026-07 row (WSJ/CNBC talks reported 2026-07-27 of a speculative up-to-$250B backstop for a rumored 10GW campus); the signed terms differ materially ($105B not $250B; 4.25GW initial plus an unquantified 3.8GW discretionary option, not a flat 10GW; a specific 20-year OpenAI lease rather than open-ended talks), so that row's status was changed to superseded rather than deleted or merged. The single largest binding row on the ledger by guarantee ceiling. Scale check: Nvidia's own $500B multi-year compute-financing framework (nvidia-compute-financing-platforms-2026-08, announced 8-10) and its reported $250B-scale backstop talks for this same project (7-27) both preceded this at similar or larger magnitude, so $105B as the final signed number is consistent with, not an outlier against, Nvidia's disclosed scale of activity this cycle. Arithmetic check: $105B / 4.25GW = ~$24.7M per MW over the full 20-year guarantee horizon, i.e. ~$1.24M/MW/year, which sits inside the ledger's $200k-$20M/MW/year sanity band (this is a guarantee ceiling amortized over the lease term, not a services price, so it is compared loosely rather than treated as a strict services rate). Cross-source: SEC 8-K (primary) plus independent CNBC and Bloomberg reporting (tier-1), both citing the same $105B/4.25GW figures; earlier $250B/$120B figures circulating 7-27 through 8-14 were pre-signing negotiation leaks per WSJ and are explicitly superseded by the SEC-filed number.

Conditions: Nvidia entered residual value guaranties with SB Energy covering leases for approximately 4.25 GW of IT load at the PORTS-Pike Technology Campus (the former Portsmouth Gaseous Diffusion Plant) in Pike County, Ohio, capped at $105B in aggregate; payments trigger only if OpenAI, the 20-year tenant, defaults or becomes insolvent, so the $105B is a contingent guarantee ceiling, not a committed cash outlay. Nvidia can extend further credit support to roughly 3.8 additional GW at its sole discretion (unquantified in dollars, not included in this row's value); full campus is planned at up to 8 GW by decade's end. Alongside the guaranty, Nvidia is investing $1.5B in direct equity in SB Energy (joining existing investors SoftBank Group and OpenAI); separately, SoftBank/SB Energy have committed $4.2B to regional grid infrastructure. Neither the $1.5B equity stake nor the $4.2B grid commitment is included in this row's value, which covers the lease-guarantee instrument only. First 800MW of capacity targeted online in 2028 (year-precision only; no specific month disclosed). Circular by construction: Nvidia guarantees the lease, invests equity in the landlord, and is the exclusive chip supplier hosted on the campus.

2026-07-27Superseded↻ Circular

Nvidia (Financier) · OpenAI (Buyer) · SB Energy (Developer)

Value
up to $250B
Capacity / term
10 GW
First revenue
not disclosed

SUPERSEDED, excluded from binding aggregates: Nvidia in talks to guarantee up to $250B of financing so OpenAI can lease the SoftBank-subsidiary SB Energy 10 GW Ohio campus. Circular by construction: the guarantor's chips are the campus's payload. Nvidia fell 5% on the report. UPDATE 2026-08-17: the talks formalized into a signed SEC-disclosed deal with materially different terms ($105B guarantee ceiling, not $250B; 4.25GW initial with an unquantified 3.8GW discretionary option, not a flat 10GW) -- see nvidia-openai-sb-energy-ohio-2026-08, which is the binding row going forward. This row is kept, not deleted, as the on-record history of the reported negotiating range.

Conditions: Early talks per WSJ reporting; nothing signed. Backstop would cover lease and construction financing so OpenAI can lease a planned $500B, 10 GW SB Energy campus in Pike County, Ohio (800 MW first phase targeted 2028). Parallel talks reportedly cover up to $350B of chip financing.

Read our coverage →

Company-Stated Totals

$439B (total backlog, as of 2026-09-02) as stated by the company. These snapshots overlap the discrete deals above, which is exactly why the ledger never adds them to anything.

Our Coverage

Part of the free AI Compute Deal Ledger by Regards of Wallstreet, licensed CC BY 4.0. Cite it, chart it, link it.